|

|
|
|
New Rosehill Elementary School
Omaha, Nebraska
This project consisted of the
construction of a two-story building addition for Rosehill Elementary School at
56th Street and Corby Street. As part of the 1999 OPS Facilities Bond Program,
the old main school building was demolished and the new facility was
constructed on the existing site. The existing gymnasium was retained and a new
corridor connects the new school building to the existing structure. With a
footprint of 17,000 square feet for a two-story structure, the addition
utilizes structural steel beams and columns for the building skeleton. In
addition, masonry was used for exterior wall construction as well as
cast-in-place concrete for a portion of the second floor exterior. Thiele
Geotech, Inc. provided the materials testing and special inspections during the
construction phase in addition to the geotechnical exploration in the design
stage of the project. The project was completed in 2002.
|
|
|
Lowe's Northwest
Omaha, Nebraska
This home improvement warehouse
has a sales floor of roughly 115,000 square feet with a building total of
135,200 square feet. A garden center on the north side will cover an additional
27,900 square feet. The building is a single story slab on grade structure.
Conventional steel beam and column construction was used with masonry exterior.
Paved parking lots and access drives were provided around the site. The site
includes a parking lot for 650 vehicles provided east and north of the
building. A truck dock was constructed near the northwest corner of the
building. Extensive site grading was required to prepare the site and level the
building pad. Rough grading was conducted in conjunction with overlot grading
of the Grayhawk development that surrounds and includes the subject parcel.
Cuts of up to 20 feet and fills of up to 26 feet were required within the
building footprint as well as around the remainder of the site. Thiele Geotech,
Inc. performed the geotechnical exploration for this project during design.
During the construction phase of the project, Thiele Geotech, Inc. provided
materials testing, floor flatness testing, and special inspections. Completion
of the project occurred in 2002.
|
|
|
Nebraska Machinery
Omaha, Nebraska
Thiele Geotech, Inc. performed
the geotechnical exploration study for the proposed Headquarters, Sales, and
Service facility for Nebraska Machinery Company located near 156th & Sapp
Brothers Drive in Omaha, Nebraska. The project site contains roughly 40 acres
near the junction of Interstate 80 and Highway 370. The main structure contains
roughly 120,000 square feet, and includes offices, parts warehouses, and two
separate service areas. A utility building containing 14,000 square feet and a
used parts building containing 12,000 square feet were also constructed. The
building is surrounded by extensive paved drive, parking, and storage areas.
The main building and the utility building were constructed using precast
concrete wall panels with conventional steel joists, beams, and columns.
Service bays in these buildings range from 30 to 60 feet wide. Bridge cranes
are positioned over each of the service bays with capacities ranging from 5 to
15 tons. The buildings have an eave height of 30 feet and some mezzanine areas
were provided. The original topography was fairly rugged where extensive
earthwork was required to level the building pads and prepare the surrounding
paved areas. Cuts and fills between 10 feet and 25 feet were required in the
main building pad, the utility building pad, the used parts building, and
various surrounding paved areas of the site. In addition to the geotechnical
exploration, Thiele Geotech, Inc. also provided materials testing and special
inspection services for this project that is scheduled to be completed in 2002.
|
|
|
Field Maintenance Facility
Eppley Airfield
Omaha, Nebraska
Thiele Geotech, Inc. performed a
geotechnical exploration study for the field maintenance facility located on
Eppley Airfield in Omaha, Nebraska. The project consists of a new field
maintenance building with vehicle storage and administrative offices. The
building is a slab on grade structure with a footprint of 100,000 square feet.
Site work required overexcavation of approximately two to three feet for the
building slab. The majority of the building incorporates a single story, but
several small mezzanines are provided for storage and other support spaces. The
perimeter walls consist of precast concrete panels with a height of roughly 30
feet. Steel trusses are supported on the precast panels and on interior beams
and columns. Some masonry was used around the office areas. A bridge crane with
precast concrete beams and columns was provided in the interior. Materials
testing and special inspection services were also provided for this facility,
which was completed in 2002.
|
|
|
Wilson Packing Plant Redevelopment
Omaha, Nebraska
Thiele Geotech, Inc. conducted
Phase II Environmental Site Assessments (ESA) and completed a geotechnical
exploration study for the proposed Wilson Packing Plant redevelopment located
near 27th & Y Street in Omaha, Nebraska. The project involves redeveloping
the existing Wilson Packing Plant site into an industrial park. The purpose of
the Phase II ESA was to address environmental concerns related to potential
petroleum hydrocarbon releases from above ground storage tank (AST) systems and
other waste issues onsite. The site currently consists of a multi-story
building with associated facilities that were utilized as an animal processing
facility and is situated on an irregularly shaped 17-acre industrial lot.
Proposed redevelopment consists of demolition of the existing facilities,
grading the site for industrial lots, and construction of public improvements.
Public improvements will consist of installation of new sanitary and storm
sewers to support the development and pavement construction. Due to the
considerable quantity of concrete structures and pavements across the site much
of the concrete will be crushed and recycled as aggregate fill. Approximately
50,000 cubic yards of crushed concrete fill is anticipated. Roughly 40,000
cubic yards of fill will be required to fill the deep basement of the main
building. Additional earthwork will include shallow cuts from the higher
elevations along the south side of the site and fills along the low-lying north
side. Completion for the redevelopment is anticipated for 2003.
|
|
|
Q Street Improvements
Millard Avenue to 156th Street
Omaha, Nebraska
This is a federally funded
street project for the City of Omaha on one of southwest Omaha's most congested
streets. It is a major east-west arterial in the area with limited right-of-way
and major utility relocation. This 2-mile, four-lane urban roadway included
2,570 lineal meters of new storm sewer, more than 19,500 cubic meters of
concrete, 8,350 square meters of trails, and 70,100 square meters of concrete
pavement. Extensive use of retaining walls and noise barriers was required
around residential portions of the project. There were also access points for
commercial properties along both ends of the project. Thiele Geotech, Inc.
provided materials testing services during the construction phase of the
project. In addition, Thiele Geotech, Inc. prepared the retaining wall design
for a congested intersection adjacent to apartment complex near the west end of
the alignment. Project completion occurred in 2002.
|
|
|
Broadmoor Hills Office Buildings
Omaha, Nebraska
Thiele Geotech, Inc. provided
geotechnical and material engineering services on three and four-story office
buildings. Extensive earthwork was required to level this sloping site. Thiele
Geotech, Inc. conducted geotechnical exploration studies, and recommended a
drilled pile foundation to support the four-story structure. The three-story
structure was supported on a shallow foundation after improving the bearing
soils by overexcavating and recompacting. Construction phase services included
special inspections of pile foundations, structural steel, reinforced concrete,
and earthwork. The sloping site required several retaining walls for grade
separation. Thiele Geotech, Inc. designed these as geogrid reinforced segmental
retaining walls and prepared shop drawings. Construction of the four-story
building was completed in 1999 while the three-story building was completed in
2000.
|
|
|
Giles Road
Sarpy County, Nebraska
Thiele Geotech, Inc. performed
detailed design and prepared shop drawings for segmental retaining walls on
Giles Road between 72nd Street and 84th Street. Widening of the roadway to 4
lanes necessitated earth-retaining structures at 10 different locations. Over
27,000 square feet of segmental retaining walls will be constructed, ranging
from 4 feet to over 20 feet in height. To meet space restrictions at an
existing cemetery, a steel sheet-pile system was installed using segmental
block facing connected with geogrid straps. Segmental retaining walls are
designed as a geogrid reinforced mass that acts as a gravity structure. The
design evaluated overturning and sliding of the reinforced mass (external
stability), geogrid stress and development length (internal stability), and the
connection required to attach the segmental units to the reinforced soil mass
(facing stability). Construction began in 1998 and with completion in 1999.
|
|
|
Hilton Garden Inn
Omaha, Nebraska
Thiele Geotech, Inc. performed
the geotechnical study and environmental assessment for the Hilton Garden Inn
in downtown Omaha. The facility is an eight-story hotel with an attached
parking garage. Several existing structures on the half block site were
demolished to make room for the hotel. During construction, Thiele Geotech,
Inc. provided special inspection services for pile foundations, concrete,
reinforcing steel, structural steel, and structural masonry. Construction was
completed in 2001.
|
|
|
Sarpy County Industrial Park
Sarpy County, Nebraska
Thiele Geotech completed several
geotechnical studies focused on design of the Sarpy County Industrial Park and
related improvements for the Caterpillar Claas America Manufacturing Facility.
Site development consisted of 1.5 million cubic yards of earthwork,
installation of sewers, construction of a bridge across the South Papillion
Creek, and 3,000 feet of new paved roadway. A 40,000 square foot building was
constructed to serve as a temporary assembly building during construction of
the 450,000 square foot manufacturing plant. Separate exploration studies were
performed for site preparation, for the public improvements, for the temporary
plant building, and for the manufacturing plant. Thiele Geotech, Inc. provided
recommendations on earthwork, construction of public improvements, pile
foundations for the bridge structure, embankment settlement, overexcavation to
improve building pads, and shallow foundations to support buildings. Thiele
Geotech, Inc. provided earthwork and material testing during construction of
the development and for the main manufacturing facility. An environmental site
assessment was also performed prior to the purchase of the 160-acre property.
The first facility opened in 1998, and construction of the main plant was
completed in 2001.
|
|
|
Stockyards Industrial Park Redevelopment
Omaha, Nebraska
Thiele Geotech, Inc. performed
an extensive environmental site assessment of the existing stockyards site in
advance of redevelopment. Past use of the property had resulted in several
environmental issues, including underground storage tanks, above ground storage
tanks, waste solvent drums, and miscellaneous small quantity wastes. Thiele
Geotech, Inc. provided an assessment of the site, characterization and
inventory of wastes, and coordination of site cleanup and waste disposal. The
study and waste removal were completed in 1998. During demolition of the old
facilities, Thiele Geotech, Inc. provided material testing and consulting
services. Concrete debris was crushed and processed for reuse as structural
fill. Thiele Geotech, Inc. also performed a geotechnical study for the
development. Overlot grading and construction of public improvements were
completed in 2002.
|
|
|
|
|
|